Term ends Jun 1, 2031 · Medium confidence
20-year base term ends Feb 1, 2031
Why Medium: A parent in the chain could not be resolved.
Filed Jul 3, 2019 as application 16/502,498 · Granted Jul 1, 2025
Base term plus 120 days of patent term adjustment (USPTO delay)
Today
2011
2031
Clock starts
Feb 1, 2011
Feb 1, 2011
Term ends
Jun 1, 2031
Jun 1, 2031
Granted
Jul 1, 2025
Jul 1, 2025
base term
patent term adjustment
Updated Nov 21, 2026 · includes USPTO assignment data published Nov 20, 2026, status data published Nov 21, 2026 and grant & fee data published Nov 17, 2026 (weekly) · how we know
120
Days of term adjustment
Read from the USPTO patent term adjustment record, not recalculated here.
None
Terminal disclaimer
No disclaimer on this record.
0 of 1
Maintenance fees paid
One maintenance fee can end this term early, the one due 3.5 years from grant; the next one's grace period runs past the term end. This counts it if the record shows it paid.
3
Family applications on record here
Applications sharing this one's continuity chain, as the file histories and patent records this site holds name them. The family may have others.
This patent's term runs 120 days past its 20-year base term on prosecution delay. 0 of 1 maintenance fees are paid so far. Confidence: Medium. from the record
How we calculated this date
One row per rule, each showing its own input and what it did to the date. A step we could not verify says so instead of resolving itself.
| Step | Input | Date after this step | Confidence |
|---|---|---|---|
| Base term, 20 years from filing | Clock starts Feb 1, 2011, when application PCT/IB2011/050437, the earliest non-provisional in its chain, was filed (this one was filed Jul 3, 2019); a parent in its chain could not be resolved (the next row) | Feb 1, 2031 | High confidence |
| Continuity chain | A parent in the chain could not be resolved | dated from this application's own claim | Medium confidence |
| Patent term adjustment | +120 days, USPTO patent term adjustment record | Jun 1, 2031 | High confidence |
| Terminal disclaimer cap | None on record | no cap applied | High confidence |
| Patent term extension | None on file | no change | High confidence |
| Fee events | 0 of 1 maintenance fees paid | In force | High confidence |
| Computed term end | The steps above, in order | Jun 1, 2031 | Medium confidence |
Partial family
| Application PCT/IB2011/050437 | PCT application no patent term | no patent term |
| US 10,385,120 | In force Dec 2032 | Dec 2032 |
| US 12,344,661 | this patent Jun 2031 | Jun 2031 |
Partial: 1 of the 3 has no file history here, so its row comes from the patent's own record or names the application alone. The family may have others.
Sources
Google Patents · The patent document at USPTO · Assignment records at USPTO
USPTO account required: This application in Patent Center · USPTO's maintenance fee lookup
Maintenance fee events come from USPTO's own fee records. Its fee lookup asks for the patent number and the application number.
Free plan: 3 watched companies. Pro: unlimited.
Alerts on its grants, lapses and transfers.
What's changing
Jun 2031
Term ends Jun 1, 2031. Maintenance fees still fall due before then
Note
The 120 days of patent term adjustment (USPTO delay) are read from the USPTO record, not recalculated by us
Citations
0
later US patents cite this one
Fewer than half of the utility patents granted in 2025 in our data have been cited yet, so we show the count and do not rank on it.
How we rank
Every date shows its work: the base term, any term adjustment or extension, any disclaimer cap, and the maintenance fee record, each with a confidence tier. How this record was built
Computed patent terms end on the dates shown. Related patents and pending applications may cover overlapping subject matter.
In force means the term is running and no lapse is on record. It is not a finding that the patent is valid.