Term ends Aug 11, 2029 · High confidence
20-year base term ends Mar 18, 2027
Held by Content Square Israel Ltd.
Filed Mar 18, 2007 as application 11/687,652 · Granted May 10, 2011
Base term plus 877 days of patent term adjustment (USPTO delay)
Today
2007
2029
Clock starts
Mar 18, 2007
Mar 18, 2007
Term ends
Aug 11, 2029
Aug 11, 2029
Granted
May 10, 2011
May 10, 2011
base term
patent term adjustment
fee events
Updated Nov 15, 2026 · includes USPTO assignment & status data published Nov 15, 2026 and grant & fee data published Nov 10, 2026 (weekly) · how we know
877
Days of term adjustment
Read from the USPTO patent term adjustment record, not recalculated here.
None
Terminal disclaimer
No disclaimer on this record.
3 of 3
Maintenance fees paid
Three maintenance fees fall due, at 3.5, 7.5 and 11.5 years from grant. This counts the ones the record shows paid.
8
Family applications on record here
Applications sharing this one's continuity chain whose file history this site holds. The family may have others.
This patent's term runs 877 days past its 20-year base term on prosecution delay. All three maintenance fees are recorded paid; no more fees are due. Confidence: High. from the record
How we calculated this date
One row per rule, each showing its own input and what it did to the date. A step we could not verify says so instead of resolving itself.
| Step | Input | Date after this step | Confidence |
|---|---|---|---|
| Base term, 20 years from filing | Clock starts Mar 18, 2007, when this application, 11/687,652, was filed | Mar 18, 2027 | High confidence |
| Continuity chain | Every parent in the chain resolved | no change | High confidence |
| Patent term adjustment | +877 days, USPTO patent term adjustment record | Aug 11, 2029 | High confidence |
| Terminal disclaimer cap | None on record | no cap applied | High confidence |
| Patent term extension | None on file | no change | High confidence |
| Fee events | 3 of 3 maintenance fees paid | In force | High confidence |
| Computed term end | The steps above, in order | Aug 11, 2029 | High confidence |
This family
| US 7,941,525 | this patent Aug 2029 | Aug 2029 |
| US 9,508,081 | In force Sep 2030 | Sep 2030 |
| US 10,749,976 | In force Apr 2027 | Apr 2027 |
| Application 16/931,064 | Abandoned not computed | not computed |
| US 11,258,870 | In force Mar 2027 | Mar 2027 |
| US 11,343,339 | In force Mar 2027 | Mar 2027 |
| US 11,516,305 | In force no later than Mar 2027 | no later than Mar 2027 |
| US 11,863,642 | In force Mar 2027 | Mar 2027 |
The applications whose file history this site holds. The family may have others.
Assignments
Assignment documents as recorded at the USPTO, oldest first, with the reel and frame each was recorded at. A recorded assignment is a filed document, not a statement of current ownership, and the absence of a later one is not evidence that the last one still stands.
| Recorded | Assignor | Assignee | Conveyance |
|---|---|---|---|
| Aug 29, 2007 Reel 19758, frame 355 | Yavilevich, Arik, MR. | Clicktale Ltd. | Assignment of Assignor's Interest |
| Feb 5, 2013 Reel 29759, frame 609 | Clicktale Ltd. | Plenus Management | Security Agreement |
| Feb 20, 2013 reel/frame not recorded | Clicktale Ltd. | Plenus III (2), Limited Partnership | Corrective Assignment to Correct the Assignees Previously Recorded on Reel 029759, Frame 0609. Assignors Hereby Confirms the Security Agreement. |
| Feb 20, 2013 reel/frame not recorded | Clicktale Ltd. | Plenus III (D.C.M), Limited Partnership | Corrective Assignment to Correct the Assignees Previously Recorded on Reel 029759, Frame 0609. Assignors Hereby Confirms the Security Agreement. |
| Feb 20, 2013 reel/frame not recorded | Clicktale Ltd. | Plenus Iii, Limited Partnership | Corrective Assignment to Correct the Assignees Previously Recorded on Reel 029759, Frame 0609. Assignors Hereby Confirms the Security Agreement. |
| Feb 20, 2013 reel/frame not recorded | Clicktale Ltd. | Plenus II (D.C.M.) Limited Partnership | Corrective Assignment to Correct the Assignees Previously Recorded on Reel 029759, Frame 0609. Assignors Hereby Confirms the Security Agreement. |
| Feb 20, 2013 reel/frame not recorded | Clicktale Ltd. | Plenus Ii, Limited Partnership | Corrective Assignment to Correct the Assignees Previously Recorded on Reel 029759, Frame 0609. Assignors Hereby Confirms the Security Agreement. |
| Feb 20, 2013 reel/frame not recorded | Clicktale Ltd. | Plenus III (C.I.), L.P. | Corrective Assignment to Correct the Assignees Previously Recorded on Reel 029759, Frame 0609. Assignors Hereby Confirms the Security Agreement. |
| Feb 20, 2013 Reel 30165, frame 80 | Clicktale Ltd. | Plenus III (2), Limited Partnership; Plenus III (D.C.M), Limited Partnership; Plenus Iii, Limited Partnership; Plenus II (D.C.M.) Limited Partnership; Plenus Ii, Limited Partnership; Plenus III (C.I.), L.P. | Corrective Assignment to Correct the Assignees Previously Recorded on Reel 029759, Frame 0609. Assignors Hereby Confirms the Security Agreement. |
| Jul 7, 2015 Reel 36008, frame 618 | Plenus Management; Plenus Ii, Limited Partnership; Plenus II (D.C.M.), Limited Partnership; Plenus Iii, Limited Partnership; Plenus III (D.C.M.), Limited Partnership; Plenus III (2), Limited Partnership; Plenus III (C.I.), L.P. | Clicktale Ltd. | Release of Security Interest |
| Apr 6, 2016 Reel 38372, frame 406 | Clicktale Ltd. | Silicon Valley Bank | Security Agreement |
| Dec 7, 2016 Reel 40588, frame 765 | Clicktale Ltd. | Silicon Valley Bank | Security Interest |
| Jun 26, 2018 Reel 46197, frame 698 | Clicktale Ltd. | Bank Leumi le-Israel B.M. | Security Interest |
| Jun 28, 2018 Reel 46222, frame 581 | Clicktale Ltd. | Kreos Capital V (Expert Fund) L.P. | Security Interest |
| Feb 6, 2019 Reel 48264, frame 432 | Silicon Valley Bank | Clicktale Ltd. | Release of Security Interest |
| Oct 26, 2020 Reel 54203, frame 248 | Bank Leumi le-Israel B.M. | Clicktale Ltd. | Release of Security Interest |
| Jan 26, 2021 Reel 55118, frame 286 | Clicktale Ltd. | Content Square Israel Ltd. | Change of Name |
Sources
Google Patents · The patent document at USPTO · Assignment records at USPTO
USPTO account required: This application in Patent Center · USPTO's maintenance fee lookup
Maintenance fee events come from USPTO's own fee records. Its fee lookup asks for the patent number and the application number.
Free plan: 3 watched companies. Pro: unlimited.
Alerts on its grants, lapses and transfers.
What's changing
Aug 2029
Term ends Aug 11, 2029. No further fees fall due before then
Note
The 877 days of patent term adjustment (USPTO delay) are read from the USPTO record, not recalculated by us
Citations
339
later US patents cite this one
That is top 1% of utility patents granted in 2011 in our data, the only group it is compared against.
How we rank
Every date shows its work: the base term, any term adjustment or extension, any disclaimer cap, and the maintenance fee record, each with a confidence tier. How this record was built
Computed patent terms end on the dates shown. Related patents and pending applications may cover overlapping subject matter.
In force means the term is running and no lapse is on record. It is not a finding that the patent is valid.