Also listed on Galvion Power Systems Inc., an earlier holder on the record. The recorded assignments below show how it moved.
Collateral for a security interest recorded Aug 26, 2022 (Bank of America, N.A.).
Term ends Apr 13, 2031 · High confidence
20-year base term ends Jun 7, 2030
Held by Stryten Energy LLC
Filed Jun 7, 2010 as application 12/795,533 · Granted Apr 23, 2013
Base term plus 310 days of patent term adjustment (USPTO delay)
Today
2010
2031
Clock starts
Jun 7, 2010
Jun 7, 2010
Term ends
Apr 13, 2031
Apr 13, 2031
Granted
Apr 23, 2013
Apr 23, 2013
base term
patent term adjustment
fee events
Updated Nov 16, 2026 · includes USPTO assignment & status data published Nov 16, 2026 and grant & fee data published Nov 10, 2026 (weekly) · how we know
310
Days of term adjustment
Read from the USPTO patent term adjustment record, not recalculated here.
None
Terminal disclaimer
No disclaimer on this record.
3 of 3
Maintenance fees paid
Three maintenance fees fall due, at 3.5, 7.5 and 11.5 years from grant. This counts the ones the record shows paid.
This patent's term runs 310 days past its 20-year base term on prosecution delay. All three maintenance fees are recorded paid; no more fees are due. Confidence: High. from the record
How we calculated this date
One row per rule, each showing its own input and what it did to the date. A step we could not verify says so instead of resolving itself.
| Step | Input | Date after this step | Confidence |
|---|---|---|---|
| Base term, 20 years from filing | Clock starts Jun 7, 2010, when this application, 12/795,533, was filed | Jun 7, 2030 | High confidence |
| Continuity chain | Every parent in the chain resolved | no change | High confidence |
| Patent term adjustment | +310 days, USPTO patent term adjustment record | Apr 13, 2031 | High confidence |
| Terminal disclaimer cap | None on record | no cap applied | High confidence |
| Patent term extension | None on file | no change | High confidence |
| Fee events | 3 of 3 maintenance fees paid | In force | High confidence |
| Computed term end | The steps above, in order | Apr 13, 2031 | High confidence |
Assignments
Assignment documents as recorded at the USPTO, oldest first, with the reel and frame each was recorded at. A recorded assignment is a filed document, not a statement of current ownership, and the absence of a later one is not evidence that the last one still stands.
| Recorded | Assignor | Assignee | Conveyance |
|---|---|---|---|
| Jan 30, 2014 Reel 32085, frame 974 | Carkner, Steve | Panacis Inc. | Assignment of Assignor's Interest |
| May 5, 2017 Reel 42417, frame 344 | Panacis Inc. | Revision Electronics & Power Systems Inc. | Change of Name |
| May 26, 2017 Reel 42515, frame 288 | Revision Electronics & Power Systems Inc. | Revision Military S.A.R.L. | Assignment of Assignor's Interest |
| Aug 16, 2019 Reel 50072, frame 679 | Revision Miltary S.A.R.L. | Revision Electronics & Power Systems Inc. | Assignment of Assignor's Interest |
| Jun 25, 2020 Reel 53038, frame 1 | Revision Electronics & Power Systems Inc. | Galvion Power Systems Inc. | Change of Name |
| Jul 6, 2021 Reel 56769, frame 1 | Galvion Power Systems Inc. | The Toronto-Dominion Bank | Confirmation of Grant of Security Interest |
| Apr 8, 2022 Reel 59539, frame 367 | Galvion Power Systems Inc. | Stryten Canada Inc. | Assignment of Assignor's Interest |
| Apr 8, 2022 Reel 59539, frame 546 | Stryten Canada Inc. | Stryten Energy LLC | Assignment of Assignor's Interest |
| Aug 12, 2022 Reel 61164, frame 736 | The Toronto-Dominion Bank | Galvion Power Systems Inc. | Release of Security Interest |
| Aug 26, 2022 Reel 60909, frame 738 | Stryten Energy LLC | Piney Lake Opportunities Eci Master Fund LP | Security Interest |
| Aug 26, 2022 Reel 60911, frame 616 | Tulip Molded Plastics Corporation | Bank Of America, N.a. | Security Interest |
| Aug 26, 2022 Reel 60911, frame 753 | Stryten Energy LLC | Bank Of America, N.a. | Security Interest |
| Jun 14, 2023 Reel 63950, frame 691 | Galvion Power Systems Inc. | The Toronto-Dominion Bank | Release of Security Interest |
| Dec 18, 2024 Reel 69735, frame 432 | Stryten Energy LLC; Tulip Molded Plastics LLC | Silver Point Finance, LLC, as the Agent | Grant of Security Interest– Patents |
| Dec 23, 2024 Reel 69754, frame 767 | Piney Lake Opportunities Eci Master Fund LP, as Agent | Stryten Energy LLC | Release of Security Interest in Patents, Recorded at Reel / Frame 060909/0738 |
Sources
Google Patents · The patent document at USPTO · Assignment records at USPTO
USPTO account required: This application in Patent Center · USPTO's maintenance fee lookup
Maintenance fee events come from USPTO's own fee records. Its fee lookup asks for the patent number and the application number.
What's changing
Apr 2031
Term ends Apr 13, 2031. No further fees fall due before then
Note
The 310 days of patent term adjustment (USPTO delay) are read from the USPTO record, not recalculated by us
Citations
5
later US patents cite this one
That is below the median of utility patents granted in 2013 in our data, the only group it is compared against.
How we rank
Every date shows its work: the base term, any term adjustment or extension, any disclaimer cap, and the maintenance fee record, each with a confidence tier. How this record was built
Computed patent terms end on the dates shown. Related patents and pending applications may cover overlapping subject matter.
In force means the term is running and no lapse is on record. It is not a finding that the patent is valid.